DOZENS of roads across Chester and Ellesmere Port are to be resurfaced as part of an extensive council programme this spring.
Cheshire West and Chester Council is due to begin preparation work over the next couple of weeks for its resurfacing programme to get the roads ready for when warmer weather arrives.
The council’s Highways Department will be treating some road surfaces with a micro asphalt surface treatment in the spring.
Micro asphalt surface treatment is a road maintenance process which involves laying a thin layer over the top of the existing road to seal the surface and restore grip, thereby extending the active lifespan of the road.
Preparation work includes cutting back overhanging trees, plus clearing debris and dirt at the edges of the carriageway.
Cllr Karen Shore, deputy leader and Cabinet Member for Environment, Highways and Strategic Transport, said: “Undertaking regular and timely maintenance of roads using surface treatments such as micro asphalt is a far more sustainable and cost effective approach as it extends the service life of a road, rather than allowing roads to deteriorate to a poor condition requiring more costly intervention.”
Micro asphalt cures quickly and can usually be driven on less than an hour after application.
Its ability to reshape and re-profile existing surfaces ensures minor defects, such as potholes and cracks, are sealed to stop water getting in to cause further damage.
On average, micro asphalt extends the ‘life expectancy’ of a road by five to seven years.
It has a much-reduced environmental impact compared to standard resurfacing techniques as it is a non-polluting, cold-applied, zero-emissions material.
Roads which will be resurfaced in the Chester and Ellesmere Port areas are:
Little Sutton
- Welsh Road
Preparation works: Monday 3 February for 2 days
Proposed work dates: Monday 2 March - Tuesday 3 March
Ledsham
- Ledsham Hall Lane
Preparation works: Tuesday 28 January and Monday 3 February
Proposed work dates: Tuesday 3 March - Wednesday 4 March
Little Neston
- Winstanley Road
Preparation works: none required
Proposed work dates: Wednesday 4 March
- Sunningdale Way
Preparation works: Tuesday 28 January
Proposed work dates: Wednesday 4 March - Thursday 5 March
- Greenfields Drive
Preparation works: Tuesday 28 January and Friday 31 January
Proposed work dates: Thursday 5 March - Friday 6 March
Hooton
- Waterworks Lane
Preparation works: Monday 27 January and Friday 31 January
Proposed work dates: Friday 6 March - Saturday 7 March
- Oakfield Road
Preparation works: Monday 27 January and Friday 31 January
Proposed work dates: Saturday 7 March
Great Sutton
- Horstone Road
Preparation works: none required
Proposed work dates: Saturday 7 March - Sunday 8 March
- Horstone Garden
Preparation works: none required
Proposed work dates: Sunday 8 March
- Horstone Crescent
Preparation works: none required
Proposed work dates: Sunday 8 March - Monday 9 March
- Saltersgate
Preparation works: none required
Proposed work dates: Monday 9 March - Tuesday 10 March
- Humber Road
Preparation works: none required
Proposed work dates: Tuesday 10 March
- Chilton Drive
Preparation works: none required
Proposed work dates: Tuesday 10 March - Wednesday 11 March
- Antrim Drive
Preparation works: none required
Proposed work dates: Wednesday 11 March
- Cartmel Drive
Preparation works: none required
Proposed work dates: Wednesday 11 March
- Merton Road
Preparation works: Tuesday 28 January
Proposed work dates: Wednesday 11 March - Thursday 12 March
- Budworth Road
Preparation works: Wednesday 29 January
Proposed work dates: Thursday 12 March - Friday 13 March
- Falcon Road
Preparation works: none required
Proposed work dates: Thursday 12 March - Monday 16 March
- Nantwich Road
Preparation works: Friday 31 January
Proposed work dates: Monday 16 March - Tuesday 17 March
- Talbot Road
Preparation works: Wednesday 29 January - Friday 31 January
Proposed work dates: Monday 16 March - Tuesday 17 March
Ellesmere Port
- Stanney Lane Service Road 1 and 2
Preparation works: Thursday 30 January for 2 days
Proposed work dates: Tuesday 17 March - Thursday 19 March
- Stanney Lane Service Road 3
Preparation works: Monday 3 February for 2 days
Proposed work dates: Thursday 19 March - Friday 20 March
- Stanney Lane Service Road 4
Preparation works: Friday 31 January and Tuesday 4 February for 2 days
Proposed work dates: Friday 20 March - Sunday 22 March
- Sandringham Gardens
Preparation works: none required
Proposed work dates: Saturday 21 March - Sunday 22 March
- Denbigh Gardens
Preparation works: none required
Proposed work dates: Saturday 21 March
Chester
- Northgate Avenue (including Eardswick Close)
Preparation works: Friday 31 January
Proposed work dates: Monday 23 March - Tuesday 24 March
- Heron Place
Preparation works: none required
Proposed work dates: Monday 23 March - Tuesday 24 March
- Wroxham Close
Preparation works: none required
Proposed work dates: Tuesday 24 March
- Hatherton Way
Preparation works: Friday 31 January
Proposed work dates: Tuesday 24 March
- Foxwist Close
Preparation works: none required
Proposed work dates: Tuesday 24 March
- Gonsley Close
Preparation works: none required
Proposed work dates: Wednesday 25 March
- Hankelow Close
Preparation works: none required
Proposed work dates: Wednesday 25 March
- Baristow Close
Preparation works: none required
Proposed work dates: Wednesday 25 March
Churton by Farndon
- Stannage Lane
Preparation works: Wednesday 5 February, Thursday 6 February, Friday 14 February and Monday 17 February
Proposed work dates: Wednesday 25 March - Thursday 26 March
Kelsall
- Dog Lane
Preparation works: Wednesday 5 February, Thursday 6 February and Monday 17 February
Proposed work dates: Thursday 26 March - Friday 27 March
Duddon
- Burton Lane
Preparation works: Thursday 6 February, Friday 7 February and Tuesday 18 February
Proposed work dates: Friday 27 March - Monday 30 March
Tattenhall
- Oaklands Avenue
Preparation works: Tuesday 18 February
Proposed work dates: Tuesday 31 March
- Oaklands Crescent
Preparation works: Tuesday 18 February
Proposed work dates: Tuesday 31 March - Wednesday 1 April
- Rookery Drive
Preparation works: Friday 31 January
Proposed work dates: Wednesday 1 April
- Greenlands (including two cul-de-sacs)
Preparation works: none required
Proposed work dates: Thursday 2 April
Mickle Trafford
- Regency Court
Preparation works: Thursday 6 February
Proposed work dates: Thursday 2 April
- School Lane
Preparation works: Tuesday 4 Feb - Thursday 6 February
Proposed work dates: Friday 3 April
Frodsham
- Manor Road
Preparation works: none required
Proposed work dates: Saturday 4 April
- Clifton Crescent
Preparation works: Wednesday 12 February
Proposed work dates: Saturday 4 April - Sunday 5 April
- Access off Ashton Drive (rear of shops)
Preparation works: none required
Proposed work dates: Sunday 5 April
- 117-139 Ashton Drive
Preparation works: none required
Proposed work dates: Sunday 5 April
- Riversdale
Preparation works: Tuesday 11 February
Proposed work dates: Sunday 5 April
- Ashton Drive
Preparation works: Friday 7 February, Monday 10 February and Tuesday 11 February
Proposed work dates: Monday 6 April - Tuesday 7 April
- Belvedere Close
Preparation works: none required
Proposed work dates: Tuesday 7 April
- Hayes Crescent
Preparation works: Thursday 13 February
Proposed work dates: Tuesday 7 April - Wednesday 8 April
- St Hilda's Drive
Preparation works: Wednesday 12 February - Thursday 13 February
Proposed work dates: Wednesday 8 April - Thursday 9 April
- Howey Lane
Preparation works: none required
Proposed work dates: Thursday 9 April - Friday 10 April