Photos courtesy of Snowdon Curtis.

WORK on the Old Colwyn promenade and coastal defences is nearing completion, which is expected in early 2024.

The council have confirmed that the rock armour is now finishing around the fishing platform, with contractors having also built almost two thirds of the new, higher seawall (410m, with 260m to go).

MORE: New Rhos-on-Sea disability respite centre opens its doors

Access steps and a ramp for the fishing platform are nearly completed, with construction continuing on other beach access steps in the area.

Contractors are continuing to add material to raise the level of the promenade.

A Conwy County Borough Council spokesperson said: "We expect this phase of the coastal defence work at Old Colwyn to be completed in early 2024."